25th April

Report by Vince

Vince, Roz, Jon, Mike, Nick
and Tav

Nick and Tav were at the
bottom of the pit, the rate at which the buckets were being filled suggests
that it was Nick digging, Tav clearing. Jon was, also clearing and loading the
filled buckets and rocks into the skip at the top of the pit. This was hauled
up the slope by Mike. The slope was lubricated, every now and again by the
application of a little water. Mike found out later that the bucket of water had
a leak and he had a damp bottom and leg.

As they had arrived a
little later, Vince and Roz took on the spoil management role, emptying and
cleaning the buckets, distributing the sediment to ensure all available space
was being utilised fully. There was a bit of wall building too.
Roz cleans another bucket, in the background, Mike awaits the next load.

No-one counted, but a lot
of buckets were filled and emptied, rocks moved too. A lot of spoil was shifted

.

18th April

Report by Vince

Vince, Jon and Mike

Vince had prepared two skips
on Tuesday evening and these were taken into the cave. One was used to replace
the old worn-out skip we had been using, the other is a spare for later. While Vince
was fettling the skip Jon went ahead, to the bottom of the pit and started
filling bags. Mike followed on and cleared the filled bags and buckets, loading
some into the now, renewed skip. Vince hauled and emptied a few buckets that Mike
had filled to clear the runnel where the water flows in wet conditions before
moving downslope to the top of the pit. The filled bags and buckets were then
stashed at the top of the pit ready to be hauled and emptied. When all the
available receptacles were filled and stashed we all moved back to clear the
backlog. The last task was to hang the empty bags along the ladder.

About three dozen loads
were removed from the dig and added to the spoil heap. We are now in need of
some additional walling work to facilitate further spoil management, and to
prevent any potential slumping of stashed material.

A very warm session, Vince won’t
be wearing two layers of thermal tops on the next session!

11th April

Nick digging, filling buckets.

Report by Vince

Vince, Nick, Tav, Jon and Mike

Nick, returned from his
travels (work-related), was digging, I was clearing away the filled buckets, replacing
them with empty ones. The buckets were passed to Tav, at the top of the pit, he
was loading them into the skip. The skip is rapidly deteriorating and really
needs changing. Jon was at the top of the slope hauling the skip away, every
now and then, adding water to the slope to ease the passage of the loaded skip.
Mike was diligently, disposing of the spoil onto the heap, ensuring that all
available space was, well and truly, filled.

All was well until it
came to the final load tally, which turned into an ongoing debate. As nobody
seemed to have been counting, a possible compromise was reached; 60 loads (last
week’s tally) + an extra person + 20%, a total of 72 was arrived at. This was
then complicated by the fact that we had used only buckets, this was likely to
have been more efficient – a factor that hadn’t been applied. We are still
debating, it is unlikely that we are ready for a meaningful vote or asking the
people to have a vote quite yet.

It was, though an
enjoyable and productive session.

5th April

Report by Vince

Forgetting to pick-up my
camera when leaving a cave is becoming a regular occurrence. However, there are
a lot of things to appreciate while caving solo – more time to look at the
caves structure and development, time to enjoy the solitude and peace at the
end of the working week and, there is the opportunity to poke into those nooks
and crannies that you find along the way. Even though the trip has been made on
numerous occasions there is always more to discover, went along a nicely decorated
passage just off the cascade, heading towards the dig site. And, I remembered to
collect the camera too!

4th April

Report by Vince

Vince, Jon, Tav and Mike

After some heavy rain we
were, sort of, expecting there to be a puddle at the dig. Surprised to find it
dry.
Mike approaches the dig

Mike digging, Jon
clearing away and filling a few bags, then chucking the filled buckets and bags
up to Vince at the top of the pit. The filled receptacles were loaded into the
skip, this was hauled up the slope by Tav. The slope was regularly ‘lubricated’
with the addition of water. Tav also emptied the buckets and bags onto the
spoil heap.

The introduction of bags
into the spoil removal system has improved productivity. The down-side to this,
the bags get rather claggy, to try and address this, at the end of the session
the bags were hung on the ladder, placed horizontally, to ‘dry’. It might work.

At the close of the
session: 60 loads had been filled, hauled and emptied. Good effort.

28th March

Report by Vince

Vince and Jonathon

Just the two of us turned
up this evening, lots of work commitments and other things. We carried on
regardless. At the dig we decided that some spoil management would be a good
objective for this session. So, we set about shifting the spoil heap, cramming
as much as possible into available “nooks and crannies” and made plenty of
space for future digging sessions. As ever with these things there is always
more that can be done. At the end of this evening’s work the buckets were given
a scrape out. Then, to the Hunter’s.

21st March

Report by Vince

Vince, Tav, Nick and
Jonathon

On arrival at the dig
site at the top of Wookey 20, it was noted that, after a dry week, the puddle
had drained away.

Tav fills another bag

Vince was digging, Tav
assisted clearing filled bags away, and he filled a few too. Jon was at the
skip “station” loading the bags (and a few buckets) to Nick, who was hauling up
the slope and emptying the filled receptacles onto the ever-growing spoil heap.
There was some discrepancy regarding the total number of loads because no-one took
the responsibility of counting. By consensus, we arrived at a figure of
somewhere around 40 to 50 loads. Does it matter? Probably not, stuff got moved,
that’s the important bit.

Another fun evening in
Wookey Hole!

14th March

Report by Vince

Vince, Jonathon and Nick.

The “Fun Boy Three”, no “Bananas”, went math!

A total of 45 loads were excavated, hauled and emptied; we had 8 buckets and 7 bags; how many times did we fill and empty each?

From the outset we had thought it might be too wet to dig but agreed we would go and check it out anyway. it was noted, that throughout the cave there wasn’t as much water as we had anticipated. At the dig, there was a puddle but not deep enough to stop the digging activities.

Jon digging, Nick clearing the filled buckets and bags and taking care not to fall into the puddle. It was amusing watching Nick trying to extract a misplaced stepping stone from the puddle without getting wet. Vince was at the skip station stacking the filled receptacles ready for hauling and emptying.

It turned out to be a productive session and digging is easily done with a team of three, result!

7th March

Due to work committments, etc. there were not enough people available to make-up a digging team for this evening.